In February 2024, Rheinmetall laid the groundwork for its own 155 mm factory in Ukraine by signing a Memorandum of Understanding to establish a German-Ukrainian joint venture.
A six-figure number of modern 155 mm shells, along with the corresponding propellant charges, were to be produced locally each year to support the Armed Forces of Ukraine in their fight against the Russian aggression.
However, after more than 2.5 years and numerous delays, the project is now on the verge of being scrapped, before a single artillery shell has even been produced at the factory. This was announced by Rheinmetall’s CEO Armin Papperger during today’s Capital Markets Day presentation.
Although nothing seems to be set in stone yet, he did announce during the Q&A session that he believed Rheinmetall would not continue with this project.
Papperger explained that the reason for this was that the Ukrainian partners were unwilling to budge from their stance of wanting to produce everything themselves. As things stand, Ukraine already produces a great deal itself, particularly in the area of short- and medium-range artillery ammunition, and the impact of Ukraine on Rheinmetall’s business is already very limited.
According to Papperger, the Armed Forces of Ukraine are currently firing between 1 million and 1.3 million artillery shells a year, more than half of which are produced locally by Ukrainian companies, even though they continue to receive a significant amount of international assistance.

Although Rheinmetall continues to supply its own artillery ammunition to the Armed Forces of Ukraine – primarily as part of Germany’s, Denmark’s and the Netherlands’ military assistance – it appears that Rheinmetall’s plan to produce artillery ammunition locally are no longer relevant, at least as far as Ukraine is concerned.
For more than a year now, Rheinmetall has made no progress in establishing production capacity in Ukraine. In the past year alone, Papperger repeatedly highlighted the significant bureaucratic hurdles in Ukraine, which are also the reason why, back in August 2025 – after around 1.5 years – Rheinmetall did not even had a concept for the construction of the entire facility yet. Now, the project faces shutdown.
The CEO sees potential only in the supply of key components, such as presses, to help build up Ukrainian production capacity, and in the supply of very long-range artillery ammunition, for the production of which the Ukrainian industry still lacks the necessary technology.